METHOD STATEMENT FOR WIRING DEVICES INSTALLATION

METHOD STATEMENT FOR WIRING DEVICES INSTALLATION

This Method Statement for the electrical Wiring devices is uploaded by QHSE DOCUMENTS for its valuable visitors total for free in Word and ready-to-use and editable format. 

Table of Contents

1.0. PURPOSE

2.0. SCOPE OF WORK

3.0. REFERENCES

4.0. RESPONSI BLE PERSONNEL ON SITE

5.0. HEALTH AND SAFETY

6.0. STORAGE

7.0. PRE-INSTALLATION

8.0. TOOLS

9.0. INSTALLATION PROCEDURE

10.0. INSPECTION

11.0. ATTACHMENT

1.0. PURPOSE

This Method Statement covers installations of wiring devices defined by the Specifications.

2.0. SCOPE OF WORK

This procedure defines the method to be used to ensure that Wiring devices are correctly installed, acceptable, and shall conform to the specifications.

3.0. REFERENCES

4.0. RESPONSI BLE PERSONNEL ON SITE

5.0. HEALTH AND SAFETY

General HSE Statement

6.0. STORAGE

7.0. PRE-INSTALLATION

  • All materials, drawings, and documentation relevant to this particular section of work will be checked before installation.
  • Before the commencement of works, ensure that the installation area is accessible and in a suitable condition to execute the installations.
  • Ensure that wall and ceiling finishes are completed before installation.
  • Determine the exact location of the materials installed from the approved Shop Drawings.
  • Check that all wiring installations are completed and the wires have been tested for insulation and continuity test.
  • Ensure that the test forms are signed by the Consultant. 
  • The size of the wires shall fit the terminal of the devices

8.0. TOOLS

9.0. INSTALLATION PROCEDURE

10.0. INSPECTION

After the complete installation of Isolators and disconnect switches in a certain area, a request for inspection shall be raised for the consultant’s approval.

11.0. ATTACHMENT

Risk Assessment 

DOWNLOAD THE FILE

METHOD STATEMENT FOR WIRING DEVICES INSTALLATION