METHOD STATEMENT FOR INSTALLATION TESTING AND COMMISSIONING OF SPLIT AC

METHOD STATEMENT FOR INSTALLATION TESTING AND COMMISSIONING OF SPLIT AC

1. PURPOSE

The purpose of this methods statement (MS) is to describe the systematic and quality procedure for the various activities required for the installation, testing & commissioning of wall mounted split AC to ensure that all works are conducted and carried out following the contract specification, approved shop drawings and as per the Manufacturer’s Instruction.

2. SCOPE

This method statement is provided clear and sufficient details for carrying out the Supply and Installation of a [WRITE DOWN CAPACITY HERE] Split Unit.

2.1 Responsibility

It will be the responsibility of the Project Manager and Project Engineer to ensure the availability of coordinated drawings and the required materials as per the project specifications. Split Air Condition System will be commissioned by the experienced foreman/Technician under the supervision of site engineers.

3. LEGISLATION & CODE OF PRACTICE.

All work shall be carried out in accordance mentioned in the project specifications.

4. REFERENCES

•    Approved material submittal.

5. DEFINITIONS

PPE       Personal Protective Equipment 

ITP        Inspection & testing Plan

PM        Project Manager 

PE         Project Engineer 

QC        Quality Control

HSE      Health, Safety & Environment

6. RESOURCES

6.1 Materials and their approval:

Split A/C indoor/outdoor units.

6.2 Subcontractor approval:

The work will be executed by [Write down supply/Contractor/company name here].

6.3 Shop drawings:

All Work will be done as per the approved shop drawing.

6.4 Equipment:

7. SAFETY PRECAUTIONS

8. INSTALLATION PROCEDURE:

8.1 Decorative type Split Unit

8.2 Condensing Unit

8.3 Refrigerant Piping

8.4 Power / Control wiring connection

9. DETAILED TESTING AND COMMISSIONING SEQUENCE AND METHODOLOGY 

9.1 Pre-Commissioning Procedure:

a. Make sure that the indoor & outdoor AC unit installation is complete and mechanical completion is appropriately approved

b. Make a careful check for the indoor & outdoor AC units are installed as per the approved shop drawings & manufacturer‘s technical and safety instructions.

c. Check the refrigerant piping installation for the AC unit is complete with all the valves & accessories in line with the approved shop drawings and recommendations

d. Check appropriately for electrical connection between the indoor & outdoor AC units & between the outdoor unit & the power supply system.

e. Make sure that Fan coil alignment is ok as per the design and recommendations.

f. Make sure that the A/C drain point is terminated.

g. Make sure that copper piping is not pinched to avoid any blockage of flow refrigerant.

h. Make sure that all outdoor units are connected with the right indoor unit and properly installed with an anti-vibration mount.

i. Make sure the filter of the indoor unit is clean and dirt free.

j. Make sure that all windows and doors are in close condition.

9.2 Testing & Commissioning Procedure:

9.1.1 Refrigerant Pipe Leak Test

  1. Connect the vacuum pump to the refrigerant piping circuit and make sure that all the piping network gets vacuumed completely.
  2. Pressurize the AC Refrigerant piping network by charging Nitrogen up to 450 psi and hold the pressure for a minimum of twenty-four hours. After twenty-four hours check the pressures if it holds 450 psi then flush the system with nitrogen.

9.1.2 Refrigerant Charging

  1. Once the refrigerant pipes are pressure tested entire piping is flushed with nitrogen gas to remove any foreign material inside the pipes.
  2. Vacuum the system up to zero psi and wait for 20 -30minuntes then open the hand shut-off valve and release the gas. Equipment/appliance is ready for a test run.
  3. Run the equipment and check the pressure of refrigerant gas, if required some refrigerant can be topped-up

9.1.3 Commissioning Procedure

  1. Ensure that the pre-commissioning checks are carried out successfully.
  2. Ensure refrigerant copper pipes are selected as per the schedule and pressure testing and nitrogen flushing are done.
  3. After completing cable terminations and refrigerant charging, the equipment is ready to start. 
  4. Switch ON the power isolator of the Outdoor unit and make sure that the DP switch of the indoor unit
  5. Also, in switch on mode.
  6. Switch on power, press the on/off button on the wireless remote control to start the operation.
  7. Press the MODE button to select COOL/HEAT/ FAN to check whether the operation is normal or not.
  8. The thermostat switch is moved to ON position, Temperature is set at the required set point.
  9. Starting Current and Running Current is to be recorded.
  10. Observe the operation of the condensing units for cut and cut out, after completing one cycle of operation, the system is left for continuous operation.
  11. During running condition rated and Running Ampere of outdoor unit will be checked by Digital meter and recorded in the test sheet
  12. Connect the manifold kit of the pressure gauge to discharge and suction service ports and record the Suction and Discharge pressure reading in the commissioning checklist.
  13. After a certain time will check the temperature of the Room by a thermometer whether the cooling Capacity is in satisfactory condition or not.
  14. Check the indoor & outdoor units are running without any abnormal vibration or noise.
  15. Measure & record the current & voltage of the compressor.
  16. Measure & record the ON/OFF coil temperature. Measure & record the total airflow from the unit.
  17. Record all the reading in the commissioning checklist

10. PPE REQUIREMENTS

As a minimum, the following PPE should be used by staff/labours

  1. Hard hat
  2. Safety shoe
  3. Safety goggles
  4. Hand gloves
  5. High visibilities vest
  6. Dust mask
  7. Safety harness