Site icon

METHOD STATEMENT FOR DISMANTLING OF TOWER CRANE

The following is point and text derived and taken from the original and editable file for the method statement of tower crane dismantling activity. To download quality occupational, health and safety free documents such as HSE forms, training slides, checklists, risk assessments, health and safety procedures and technical guidelines, facility management related all documents, electrical MEP installations and repair work. HAVC documents etc. QHSE docs are the only site that is providing its visitors with quality and free editable documents. you just download, fill in your details and go for the official use

1-SCOPE

Dismantle 01 unit of above mention Tower Crane for the site above with due consideration to the quality and safety aspects of the proposed development.

2- WORKING METHOD

DISMANTLE OF ABOVE MENTION TOWER CRANE

2.1. Phase 1

Dismantle Using MR220 (TC 1) Tower Crane.

2.2. Phase II

3-WORKING HOURS

Working hours shall be from 08:00 am to 4:00 p.m. Working hours may be extended if the work requires so.

4- EQUIPMENT

Trailers

5- PERSONNEL

Site Supervisor

A. Approved crane erector -2

B. Lifting Supervisor – 2

C. Riggers – 2

D. Signalman – 2

6- PROGRAMME OF WORK

6.1. Carnage

One 1-trailer at a time

All lifting gears with the crane, e.g., chain ropes, slings, shackles, and tools used for dismantling will be inspected thoroughly. Load indicator of the tower crane to be set correctly before hoisting operation. A copy of the tower crane specifications and lifting capacity will be forwarded to you for verification.

6.2. Manpower

To supply a team of riggers and qualified lifting supervisors on-site during dismantling to ensure safety measures are strictly adhered to.

6.3. Safety Measures

7- HOUSEKEEPING

  1. The immediate working area is properly cleared and materials disposed of as per the legislation, regulations, and codes of practice.
  2. Tools and equipment are cleaned, checked, maintained and stored following manufacturer recommendations and workplace procedures.
  3. Documentation is completed following workplace requirements.

8. RISK ASSESSMENT/ HAZARD ANALYSIS FOR DISMANTLING OF TOWER CRANE.

Attach as reference/required documents

METHOD STATEMENT FOR DISMANTLING OF TOWER CRANE 

DOWNLOAD THE FILE HERE

METHOD STATEMENT FOR DISMANTLING OF TOWER CRANE 

Exit mobile version