Site icon

METHOD STATEMENT DRAFT FOR CONSTRUCTION

METHOD STATEMENT DRAFT FOR CONSTRUCTION



This construction-related methodology is uploaded by the QHSE Documents for its Electrical technical personnel. This Draft Construction Method Statement For General Civils, Mechanical, And Electrical Installation is in Word format and easily editable to fulfill your requirements.

Scope of Work/Project Proposal

Development of a [~185] MW solar photovoltaic (PV) plant, connected via electric cables to Transformers, Inverters, Substations, and any other required auxiliary equipment units. 

The proposed works on-site include the installation of:

  1. Mechanical structure for mounting the solar PV modules
  2. Inverter, transformer switchgear, SCADA, and other electrical and auxiliary equipment
  3. Temporary roads, perimeter fencing, trenching for ducts & cables, foundations for inverter, transformer, substations, etc. cable installations and testing.

Planned Start Date

[ADD DATE HERE]


Estimated Duration:

[Write down the planned and scheduled date]


Location of Project

[Write down the Project Location Here]

NOTE: This Construction Method Statement is to be used in conjunction with the task-specific Risk Assessment and Method Statement and the Construction Phase Plan, which will be available during the pre-construction phase.


Site Induction

  1. All personnel involved in the works will attend a site safety talk.
  2. All personnel involved must adhere strictly to site rules as defined by Company Name in the induction.
  3. All supervisors will be required to attend safety briefings and toolbox talks when site management deems it appropriate. These will allow the dynamic changes to the site to be communicated to the workforce and ensure that safe working is maintained.
  4. A Permit to Work (PTW) system will be implemented for works deemed applicable (i.e. hot works). A PTW will be completed before any works commencing when applicable and signed off daily.

Site Setup

Perimeter Fencing:

To be installed by Company [Write down the Company Name Here]

Site offices, Welfare & Signage:

  1. Company name will take delivery of all site offices, welfare, and storage from the supplier.
  2. These will be located in the hard-standing area on site to be confirmed during the pre-start meeting (see site layout drawing for proposed locations).
  3. All deliveries will be transported by the supplier. Hi-ab-equipped Lorries will be lifting the welfare units into the agreed locations as directed by the site manager.
  4. Welfare Supplier to supply lifting plan for the delivery and placement of the welfare units.
  5. The site signage board will be erected close to the site offices and appropriate signage will be cable tied to the perimeter fencing as deemed appropriate by the site manager.
  6. Site signage will be positioned from the site entrance off the main road. 
  7. The safety warnings Signs will highlight speed restrictions and associated hazards.
  8. Barriers and cones will be used to contain traffic to designated areas

Working environment and restriction


Protection of Others

  1. The plant will be present on-site for the duration of the work. Appropriate routes are to be defined at the start of the work.
  2. Site signage, warning signs, and pedestrian barriers will be set up. “Construction warning” set up at site entrance. Warning signs are to be erected along with Netlon/Plastic mesh barrier at the tree protection area.
  3. Site welfare facilities will be 20ft site offices, 20ft canteen, 20ft toilets (including separate ladies), and drying room (when required)

Emergency Procedures & General Health and Safety

  1. Normal site procedures apply.
  2. All operatives will be made aware of the site-specific fire evacuation procedures during the site induction.
  3. Site safety briefings will be given to supervisors as the progress of the work detailing site-specific hazards that arise from the works.
  4. DC voltages are more hazardous than AC voltages due to the nature of the shock, which causes contraction and can lead the victim of a shock to “hold” onto the conductor.
  5. All persons overseeing the installation work will be experienced with, or have had specific training on, working with such systems.
  6. A PTW (permit to work) system will be in place for the electrical side of the works.

Operatives / Competence

  1. All personnel have Construction Skills Certification Scheme (CSCS), Construction Plant
  2. Competence Scheme (CPCS) or relevant competency cards.
  3. The Site Manager is Site Management Safety Training Scheme (SMSTS) or equivalent and 1st Aid qualified.
  4. All electrical work will be undertaken by qualified electricians.

Materials handling and storage

Deliveries to Site:

  1. The PV modules are delivered via shipping container packaged in cardboard on pallets and will need to be offloaded and stored using the forklift.
  2. Metal purlin, piles, and other associated components for the mounting structure will be delivered in the articulated lorry and will need to be offloaded and stored using the forklift
  3. Inverter-transformer containers, Substations, and Inverters will also be delivered via articulated lorry and require a crane lift
  4. The GRP building will be delivered in flat-pack form and erected on-site using a hi-ab.
  5. All other goods (ducting, cable, etc.) will be delivered to the site secured and removable via the tail lift or utilizing the on-site plant.
  6. All deliveries will be pre-arranged in agreement with Site Management with sufficient notice. A qualified plant operator will offload deliveries into agreed storage positions.
  7. Deliveries will be made promptly to avoid any delays in installation and to ensure that the storage provisions on-site are sufficient.
  8. All deliveries are to be recorded and damaged goods are to be reported to the site manager immediately.

Site Distribution of Goods:

  1. Movement of materials will be by utilizing plants on site.
  2. PV modules should remain in their packaging until they are installed onto the support structures.
  3. All packaging will be removed and discarded daily from the work site.
  4. The support structure work and PV modules will need to be manually handled.
  5. Please refer to the manual handling assessment for this element of the work.

Storage:

  1. PV modules, structures, and other electrical equipment will be protected from the elements and securely stored by the Company name.
  2. Packaging should be kept dry to avoid collapse or compression of the packaging which might lead to damage to the equipment.
  3. All other equipment (electrical, ducting, etc.) will be stored in a secure location (locked container) until ready to be installed, location subject to site agreement (see proposed Layout plan.

Waste:

  1. Waste is to be transferred by a licensed carrier and sent to a licensed receiver. All transfer notes are to be stored and collated if applicable.
  2. The company name will provide segregated skips for the duration of the works
  3. The company name will aim to recycle as much waste as possible

Access:

  1. All routes will be kept free of obstacles and trip hazards during the period of work.
  2. Access to the site is to be via designated pedestrian and vehicle routes detailed on- the site plan.
  3. This will inevitably change throughout the works and will be communicated to all site personnel via safety briefings with the site manager.
  4. Methodology for works:

Working area – Site:

  1. Site management will provide designated access and egress routes to and from the site.
  2. The site is exposed to the elements. All personnel will be required to wear appropriate PPE to protect them from adverse weather conditions and encouraged to use sunscreen as required.
  3. Works should cease in bad weather (persistent heavy rain, storm, high winds) as instructed by the site manager.

Working area – Inverter container/GRP housing:

  1. Container/GRP housing to be installed on concrete legs/ concrete base
  2. The respective subcontractor will deliver the unit to the site on a flatbed with a Hi- ab and erect the unit onto the foundation base. Aluminum matt may be required to be supplied as a working area.
  3. Access into the housing will be required by respective equipment suppliers for their connection works and commissioning of the switchgear. Once commissioned access will be restricted.

Working area – Location for cutting metalwork:

  1. All cutting is to be carried out at the agreed location. Site management to take steps to protect materials and other trades/personnel. Sub-contractor to provide a fire extinguisher which will be present during all cutting works. A Hot works permit is to be obtained each day as required.
  2. Cutting is to be carried out on a firm surface and all cutting equipment is to be secure and stable.
  3. PPE to be worn includes gloves, a face mask or approved safety goggles, ear protectors, and steel toe cap boots. (Applicable to a specific task)
  4. All cutting equipment is to be properly maintained and PAT tested.
  5. Instructions to be followed and guards to be used.

1st Operation – Site clearance


2nd Operation – Access track


The-3rd Operation–[Project/Building/Area Name] Edge of park connection substation:


The 4th Operation – Commissioning Utility Incomer


The 5th Operation – Foundations:

The 6th Operation – Fencing:


The 7th Operation – Lifting Placing Sub Station, Inverters, and inverter-transformer station containers:


The 8th Operation – CCTV


The 9th Operation – Electrical works and trenching


Assessment.

Should you have any questions with regard to the safety of the work you are carrying out STOP and seek advice from your supervisor?


Plant List:

General:


De-Mobilization of Site:

DOWNLOAD THE FILE

METHOD STATEMENT DRAFT FOR CONSTRUCTION

Exit mobile version