METHOD STATEMENT FOR ASBESTOS HANDLING IN BUILDING DEMOLITION


METHOD STATEMENT FOR ASBESTOS HANDLING IN BUILDING DEMOLITION



1.0. Introduction

This method statement outlines the procedures and precautions to be taken for the safe handling of asbestos-containing materials during the demolition of a building. As safety engineers, our primary objective is to protect the health and well-being of workers, the surrounding environment, and the public. Asbestos presents significant health risks, and its proper handling is crucial to prevent exposure. This document provides a comprehensive plan for managing asbestos during demolition activities.

2.0. Scope

This method statement applies to all phases of the demolition process involving structures that are known or suspected to contain asbestos-containing materials. It covers the identification, removal, disposal, and monitoring of asbestos to ensure compliance with regulatory requirements and industry best practices.

3.0. Pre-Demolition Planning

3.1. Asbestos Survey

Before initiating any demolition activities, a comprehensive asbestos survey must be conducted by a certified asbestos surveyor. This survey will identify the location, type, and condition of asbestos-containing materials within the building.

3.2. Asbestos Register

Based on the survey findings, an asbestos register will be developed, detailing the locations of asbestos-containing materials and their condition. This register will serve as a reference for the removal process.

4.0. Asbestos Removal

4.1. Work Area Isolation

The work area will be isolated to prevent unauthorized access. Barricades, warning signs, and tape will be used to demarcate the restricted zone.

4.2. Personal Protective Equipment (PPE)

All personnel involved in asbestos removal will be equipped with appropriate PPE, including disposable coveralls, respiratory protective equipment (RPE), gloves, and eye protection.

4.3. Wetting and Encapsulation

Asbestos-containing materials will be wetted down using a water mist to minimize the release of asbestos fibers. Additionally, encapsulation techniques will be used to contain the asbestos and prevent fiber release.

4.4. Controlled Removal

Asbestos-containing materials will be carefully removed in small sections to minimize breakage and fiber release. Hand tools will be used to avoid generating dust.


4.5. Decontamination Facilities

Decontamination units, including airlocks, showers, and changing areas, will be set up near the work area. Workers will undergo a decontamination process after each shift.

5.0. Waste Handling and Disposal

5.1. Sealing and Packaging

All asbestos waste will be securely sealed in double bags or containers designed for asbestos disposal. Sealed bags will be clearly labeled as "ASBESTOS WASTE."

5.2. Transport

Asbestos waste will be transported in appropriately labeled vehicles, adhering to transportation regulations and guidelines.

5.3. Disposal

Asbestos waste will be disposed of at authorized waste disposal facilities licensed to handle asbestos materials.

6.0. Air Monitoring

6.1. Air Monitoring Stations

Air monitoring stations will be set up around the work area to measure asbestos fiber levels. These stations will be continuously monitored during asbestos removal activities.

6.2. Clearance Testing

After asbestos removal, a clearance test will be conducted to ensure that airborne asbestos levels are within permissible limits. Clearance will be confirmed by a certified asbestos assessor before proceeding with further demolition activities.

6.3. Documentation and Records

All aspects of asbestos handling, from survey reports to waste disposal records, will be documented and maintained as part of the project's records.

7.0. Emergency Response

An emergency response plan will be in place in case of accidental fiber release or unexpected incidents during asbestos removal.

8.0. Asbestos Impacts on Health and Environment

8.1. Health Impacts

Asbestos is a hazardous mineral fiber that, when inhaled, can cause serious health issues, including:

8.1.1. Asbestosis

A chronic lung disease characterized by scarring of lung tissue, leading to breathing difficulties and reduced lung function.


8.1.2. Lung Cancer 

Asbestos exposure is a known cause of lung cancer, especially in individuals who smoke.

8.1.3. Mesothelioma

A rare and aggressive cancer affecting the lining of the lungs, abdomen, or heart, primarily caused by asbestos exposure.

8.2. Environmental Impacts

Asbestos fibers can be released into the air during improper handling, leading to environmental contamination. These fibers can persist in the environment for a long time, posing risks to ecosystems and human health.

9.0. Control Measures

9.1. Engineering Controls

To minimize the release of asbestos fibers, the following engineering controls will be implemented:

9.1.1. Wetting

Asbestos-containing materials will be wetted down before removal to reduce the generation of airborne fibers.

9.1.2. Encapsulation 

Applying a sealant or encapsulating material to asbestos surfaces to prevent fiber release.

10.0. Personal Protective Equipment (PPE)

Appropriate PPE will be provided to workers to ensure their safety:

10.1. Respiratory Protective Equipment (RPE) 

Workers will wear respirators with filters designed to capture asbestos fibers.

10.2. Disposable Coveralls 

Coveralls will be worn to prevent skin contact and contamination.

11.0. Work Practices

Safe work practices will be strictly adhered to during asbestos handling:

11.1. Controlled Removal:
Asbestos-containing materials will be removed using controlled, non-destructive methods to minimize fiber release.

1.2. Hand Tools 

Hand tools will be used instead of power tools to reduce the generation of dust.

12.0. Air Monitoring

Continuous air monitoring will be conducted to ensure the safety of workers and the environment:

12.1. Real-Time Monitoring

Airborne asbestos fiber levels will be monitored in real-time to detect any sudden increases.

12.2. Regular Sampling

Regular air samples will be taken and analyzed to verify compliance with permissible exposure limits.

13.0. Personal Hygiene

Proper hygiene practices will be followed by workers:

13.1. Decontamination: 

Workers will undergo thorough decontamination after each shift, including showering and changing into clean clothing.

13.2. No Eating, Drinking, or Smoking

These activities will be prohibited in the work area to prevent accidental exposure.

14.0. Waste Management

Stringent waste management procedures will be followed:

14.1. Double Sealing

Asbestos waste will be double-bagged and securely sealed to prevent fiber release.

14.2. Proper Labeling

Waste containers will be clearly labeled as containing asbestos material.

15.0. Training and Awareness

Education and awareness will be crucial to prevent asbestos-related risks:

15.1. Training:

All workers will receive specialized training on asbestos hazards, handling techniques, and emergency procedures.

15.2. Awareness

Workers will be made aware of the potential risks and the importance of following safety protocols.

16.0. Emergency Response

A detailed emergency response plan will be established:

16.1. Emergency Procedures: 

Workers will be trained on how to respond to accidental fiber release or unexpected incidents.

16.2. Communication: 

Emergency contact information and procedures will be readily available to all workers.

17.0. Monitoring and Review

Regular monitoring and review of control measures will be conducted:

17.1. Supervision 

A competent supervisor will oversee asbestos handling activities and ensure proper implementation of control measures.

17.2. Ongoing Assessment

Control measures will be continuously assessed and modified as needed to maintain a safe work environment.

18.0. Training

All personnel involved in asbestos handling will undergo specialized training on asbestos awareness, proper handling techniques, emergency procedures, and the use of PPE.

19.0. Additional Technical Guidelines 

Where asbestos could be found?

Asbestos can be found in various materials and products due to its strong, heat-resistant, and insulating properties. Here are some common places where asbestos could be found:

19.1. Building Materials

  • Insulation: Asbestos was widely used in insulation materials, including pipe insulation, boiler insulation, and attic insulation.
  • Flooring: Vinyl floor tiles, adhesive, and backing materials might contain asbestos.
  • Roofing: Roofing shingles and felt often contained asbestos.
  • Ceiling and Wall Materials: Asbestos was used in textured coatings, ceiling tiles, and plaster compounds.
  • Fireproofing and Soundproofing: Asbestos was used in these materials to enhance fire resistance and sound absorption.

19.2. Mechanical Systems

Boilers and Furnaces: Gaskets, seals, and insulation in heating systems might contain asbestos.
Piping: Asbestos-containing materials were used for insulation around pipes and ducts.

19.3. Automotive Components

Brake Pads and Clutches: Older vehicles might have brake linings and clutch facings that contain asbestos.
Gaskets: Asbestos was used in gaskets to create a heat-resistant seal in engines and other systems.

19.4. Industrial Applications

Equipment Insulation: Asbestos was used to insulate industrial equipment like boilers, tanks, and pipes.
High-Temperature Applications: Asbestos was used in various industries for its heat-resistant properties.

19.5. Consumer Products

Appliances: Some older devices might contain asbestos insulation.
Textiles: Asbestos was used in fabrics like fire-resistant curtains and gloves.

19.6. Construction Materials

Cement: Asbestos cement products, such as corrugated roofing sheets and pipes, were typical in construction.
Joint Compounds: Asbestos was used in drywall common compounds and other patching materials.

19.7. Shipbuilding and Maritime Industries:

Ships: Asbestos was used extensively in ships for insulation, fireproofing, and other applications.

19.8. Miscellaneous Products

Personal Protective Equipment (PPE): Some older types of gloves, aprons, and other protective gear contained asbestos.
Fireplace Materials: Fire-resistant materials in fireplaces and stoves could contain asbestos.

It's important to note that while asbestos was widely used in the past, its use has significantly declined due to its associated health risks. However, buildings and products constructed or manufactured before the late 20th century may still contain asbestos. Asbestos-containing materials are generally safe when undisturbed, but they can release harmful fibers if damaged, deteriorated, or improperly handled. Proper identification and management of asbestos-containing materials are crucial to prevent exposure and related health issues.