Saturday, June 4, 2022

METHOD STATEMENT FOR BLOCK WORKS

This work method statement is particularly written for the Concrete Masonry Block. To download the original editable in Word format, just click on the download link that is available at the bottom of this article.


SCOPE AND OBJECTIVES

This method statement provides the controlled sequence of the methodology that will be used for the installation and testing of the Concrete Masonry Unit (CMU) Block Works activity. This is to ensure that all activities are in full compliance with applicable standards, drawings, and specifications of the project.


REFERENCES

  1. Project Specifications 
  2. Approved Shop Drawings
  3. Project QHSE Plan


HEALTH AND SAFETY HAZARDS

The followed health and safety initiatives have to be followed and complied with as applicable, and all the safety measures are highlighted significantly in the company’s Project Safety Plan.

A. Insufficient Lighting

  1. Adequate lighting to be provided to the work location.
  2. All the electrical accessories/devices and testing equipment will be of industrial type.
  3. All the cables will be concealed / above the head.

B. Task Lighting

  1. All electrical connected cables & wires to be secured/tied appropriately to avoid any severe slip and trip hazards occurrence possibility.
  2. In addition to the fixed lighting, Portable lights will be on standby.
  3. The electrical fittings used will conform to industrial standards. 

C. Emergency Arrangements

  1. Contact numbers of the person concerned are to be displayed, on each floor.
  2. Emergency Response Team (ERT) to be appointed and on standby.
  3. Emergency routes exist to be marked.


RESPONSIBILITIES / SUPERVISION

The Project Construction Manager (CM) is fully accountable and answerable for the implementation of this work method statement (WMS) and also makes sure that his project team including Engineers, Foreman, and Sub-Contractors are well aware of this WMS and that all available resources such as human, material, machinery, and equipment are readily and safely available to accomplish and finalize the work as planned and without any latency.

The Site Engineer is responsible to carry out the work as per the approved shop drawings, and following this method statement. He is also responsible to ensure adequate equipment and materials are available for blockwork installations are in place before the start of work.

The Quality Assurance and or Quality Control site/project Engineer is accountable to make sure that work blockwork has been accomplished as per the work specification and approved drawings; evaluations & inspections are done as per the ITP and offer works for the Consultant’s inspection after verification.

The Safety Engineer is responsible to ensure that all safety precautions are in place as per the project safety plan and that all personnel on-site are using the required Personal Protective Equipment like – helmets, Gloves, Shoes, and Coveralls


RESOURCES

Materials

  1. Hollow Blocks
  2. Solid Blocks
  3. Premix Cement-Sand Mortar
  4. Grout
  5. Water
  6. Ties & Anchors
  7. Horizontal Reinforcement mesh Hot Dip Galvanized
  8. Vertical Reinforcement – Steel Bars
  9. Fire Stop Sealant
  10. Filler Board

Tools & Equipment

  1. Scaffolding
  2. Mason Tools
  3. Spirit Level
  4. Transparent Hose tubes and string rope for leveling
  5. One Bagger Mixer
  6. Grinder
  7. Power Drill
  8. Cutting Machine
  9. Chisel Hammar
  10. Tower Crane
  11. Hoist for lifting materials to a higher level

Personnel

  1. Construction Manager
  2. Site Engineers
  3. QA/QC Engineers
  4. Safety Officer
  5. Site Foreman
  6. Masons (Applicators)
  7. Helpers


PROCEDURE

  1. Before installation, examine rough-in and built-in construction for piping systems to verify the actual locations of piping connections.
  2. Make sure all proper installations and cutting and leveling tools are ready for use at the site.
  3. Prepare and clean the site of all waste, obstruction, and excess concrete layers on the flooring before beginning any of the work.
  4. The next step is to leave the proper openings for equipment to be installed before completing the masonry work activity. Once you have completed the installation of required equipment, accomplish masonry to match the construction ASAP adjacent to the opening.
  5. If block work cutting is needed to provide a fit adjoining construction, the various cut units with electrical and motor-driven light machinery such as saws; and the provision of proper cleaned, sharpened, unchipped edges. Now permit and let the units be get properly dried before laying unless wetting of units in particular. 
  6. Now next Install cut units with cut surfaces and, where applicable and or possible, properly and accurately cut edges concealed.
  7. The floor slab where Concrete Masonry Unit (CMU) walls are to be built will be chipped and cleaned.
  8. Prepare a sufficient and as per the required quantity of cement, sand, and water mixture for the ready to use the material for the time of installation.
  9. Prepare the floor for installation of the first course by washing with water and keeping the area moist for proper bonding.
  10. Prepare the mortar mix. 
  11. Always make sure not to mix a large batch. 
  12. Any excess mix will be discarded. 
  13. No mix will be used after being left standing.

METHOD STATEMENT FOR BLOCK WORKS











TO DOWNLOAD MORE HEALTH AND SAFETY FREE AND EDITABLE DOCUMENTS 

👇

DOWNLOAD HERE

RISK ASSESSMENT FOR DISMANTLING TOWER CRANE

RISK ASSESSMENT FOR DISMANTLING TOWER CRANE
 RISK ASSESSMENT FOR DISMANTLING TOWER CRANE 

QHSEDOCS is a source of free occupational health safety and environmental documents. If you are an HSE manager, engineer, supervisor, formal or professional, then this blog site is very beneficial for you. just visit the blog and download your required document with just one click on the link that is given at the end of each article. Our visitors have the option to request if they don't find their required documents on the blog, or if you need any health and safety documents. just send us a request by filling out our "CONTACT FORM"  and we will upload your required document in a couple of days. To download "Risk Assessment for Dismantling Tower Crane" click on the link given at the bottom of this post.

A- Activities

1-Preparation work

  1. Workers ascend to the working area on top of the crane.
  2. Written instruction / any popping is to be signed off by R.E. before works commence.
  3. Self-jacking to lower down tower mast.
  4. Un-reeving of hoisting wire rope
  5. Loosen the hoisting wire rope and u-clip.

2-Dismantling of Counterweights by mobile crane

  1. Setting up - mobile crane (25 tons)
  2. Secure the counterweights with a sling
  3. Removed the lock pins and lifted out the bracket
  4. Slowly hoist down to the ground using a Mobile Crane (25 tons)

3- Dismantling of Counterweights (CW) by mobile crane

  1. Setting up - mobile crane (25 tons)
  2. Secure the counterweights with a sling
  3. Removed the lock pins and lifted out the bracket
  4. Slowly hoist down to the ground using a Mobile Crane (25 tons)

4-Dismantling of boom section.

  1. Secure, tension, and remove the relevant pins and spring clamps from the boom section mounting
  2. Lift using a mobile crane (25 tons) and disconnect from the slewing table, joint and slowly hoist down to the ground

5-Dismantling of counterweights by mobile crane 

  1. Setting up a mobile crane
  2. Secure the counterweight with a sling
  3. Removed the lock pin and lifted out the bracket
  4. Slowly hoist down to the ground using a mobile crane (25 tons)

6-Dismantling of the top tower 

  1. Secure, tension it, and remove the relevant pins and spring clamp from the slewing table joint
  2. Using a mobile crane slowly hoist down the tower top to the ground (25 tons)

7-Termination of power supply

  1. Terminate power supply
  2. Disconnect cable connection

8-Dismantling of hoisting winch

  1. Using a mobile crane slowly hoist down tower top to the ground (25 tons)

9-Dismantling of counter jib a) 

  1. Secure, tension, and remove the relevant pin and spring clamps from the counter jib section mounting
  2. lift using a mobile crane (2nos, 25 tons / 25 tons) and disconnect from the slewing table, joint and slowly hoist down to the ground

10- Dismantling of the operator's cabin

  1. Secure and use a mobile crane to lift out of the slewing table joint (25 tons)
  2. Using a mobile crane slowly hoist the operator cabin down to ground level (25 tons)

11- Dismantling of the slewing table assembly

  1. Secured with slings, tension it, and remove the 8 No’s of bolts and nuts from the mast joint
  2. Using a mobile crane slowly lift/disengage and hoist down to the ground (25 tons)

12-Dismantling of 6 no’s mast section by (3) hoisting operation

  1. Remove the relevant pins
  2. Use a mobile crane to slowly hoist down to the ground (25 tons)

13-dismantle and remove collars and I-beam

  1. Use a mobile crane to slowly hoist down to ground level (25 tons)

14-Loading into a 40-footer lorry

  1. The lorry moves in and out and parks within the designated loading area
  2. Put timber wedge and using a mobile crane (25 tons), hoist the component and transfer safely into the lorry

B-HAZARDS

  1. Lifting gear failure.
  2. Unsafe work practice.
  3. Height suspended load
  4. Hand/finger crush in between
  5. Slip, trip, and fall
  6. Ergonomics
  7. Crane Overturned
  8. Overhead Electrical
  9. Mechanical Failure
  10. Steel wire rope snapped
  11. Falling object
  12. Working at height

C- EFFECTS/CONSEQUENCES

  1. Workers slip and fall from height
  2. Lightning strike
  3. Damage to existing building structure/machinery.
  4. Serious injury or fatality.
  5. Workers fall from height
  6. Crush-in between counterweight
  7. Electrical shock
  8. Hit by a flying object
  9. Crush in between
  10. Falling objects, workers fall from height
  11. Hand/ finger/ eye injury.
  12. Wire rope detaches and swings through the air
  13. Crush in between the main jib
  14. The jib section of the crane may hit an overhead structure or service cable and cause asset/machinery damage

D- Current Control                

  1. Riggers must have a safety harness during climbing, working on top, or while climbing down.
  2. To immediately stop doing work during/the possibility of heavy rain, lightning strikes, or strong wind.
  3. The certified crane operator, lifting supervisor, and rigger/signalman.
  4. A competent person to ensure all is properly secure before lower-down work is done.
  5. To follow the recommended SWL from the manufacturer for wire rope and Shackles that going to be used.
  6. Visual Inspection for any kinks, wear, and broken wire.
  7. Proper PPE (safety helmet, safety boots, safety harness, hand glove)
  8. Ensure a PMA is valid, and the operator is competent
  9. planks as an additional sleeper.
  10. Barricade area below tower crane hoisting spot
  11. ensure safety harness is in used all times
  12. To check and ensure mobile crane is in a proper setup and suitable working radius
  13. barricade area below the tower crane hoisting spot level
  14. Ensure the mobile crane rests on solid and firm ground and use steel plate and solid timber planks as an additional sleeper.
  15. check all the mobile crane electrical systems, mechanical systems, safety devices, and indicators are in order.
  16. check maximum loading calculation and maximum safe working radius and confirm with mobile crane design load chart for safe operation.
  17. Use a suitable container to store small components and tools
  18. barricade area below the tower crane hoisting spot provides a signalman
  19. To check and ensure the mobile crane is in a proper setup and suitable working radius
  20. Ensure all unauthorized workers are clear from the affected work area when hoisting of the jib is in progress
  21. To ensure there is proper clearance and no interference by another crane while dismantling and hoisting of the A-frame is in progress
  22. To secure the JIB properly and lift slowly to confirm the C.G before hoisting down slowly to ground level.
  23. To ensure all unauthorized workers are clear from the affected work area
  24. use tagline to assist in hoisting
  25. To ensure small hand tools are put in the proper container or sling bag
  26. No tools or objects shall be placed in open space
  27. To check on lifting gears to be secured properly and in the right static hooking point.
  28. To confirm the physical condition of CG is in good order
  29. To use the container for small component storage
  30. To fully barricade the area below the tower crane
  31. To monitor closely while hoisting down the mast section
  32. To stand by a flagman to guide the lorry
  33. To ensure the tagline is used during hoisting
  34. The area within the mobile crane hoisting radius is to be fully barricaded to provide a signalman to assist in hoisting

E- Additional Control                      

  1. Briefing all workers on the risk and proper work method before carrying out the task
  2. To have a toolbox talk before starting work every morning.
  3. Check all equipment and tools before starting and report for any malfunction or problem immediately.
  4. Conduct safety briefings to workers before starting work.
  5. Working/Operational ground area must be barricaded and a warning sign to ensure no other activity has been carried out.
  6. Wind the wire rope properly place it on the platform and tighten it down.
  7. Provide signalman to communicate with operator and riggers during work being done.
  8. Check all the mobile crane electrical systems, mechanical systems, safety devices, and indicators are in order
  9. Check maximum loading calculation and maximum safe working radius and confirm with mobile crane design load chart for safe operation.
  10. Tools like hammers must be fitted with good-quality wooden handles.
  11. No tools or objects shall be placed in open space
  12. Provide signalman
  13. Use tagline to assist in hoisting
  14. Proper PPE (safety helmet, safety boots, safety harness, hand glove)
  15. Tools to be secure / tie-off avoiding falling to the ground.
  16. Competent person to ensure all power in a proper earthing.
  17. Stop immediately if there is strong wind/ possibility of bad weather
  18. To ensure all unauthorized workers are clear from the affected work area
  19. To clear any loose object from the slewing table
  20. Use the container to place small components
  21. Signalman to blow whistles and clear all unauthorized workers in the affected work area.
  22. To clear and housekeeping at the loading area
  23. Put barricade/ warning sign
  24. Use the whistle to warn nearby workers/public
  25. To provide a flagman to control and manage traffic.

Download File

Friday, June 3, 2022

HEAT-RELATED ILLNESS TRAINING PPT

The human body burns calories and generates heat to retain 98.6 Fahrenheit temperature.

Two effective ways the body rids itself of heat are: 

  1. Sweating - Sweat evaporating from the skin cools the body.
  2. The Dilation of human blood vessels – The human Blood is brought to the skin's surface to discharge the heat.

A. Warning Signs

Problems establish when the human body’s cooling mechanisms aren’t capable to work appropriately, for example, when:

  1. Air temperature exceeds body temperature - the body cannot easily cool itself 
  2. Air is humid - sweat doesn’t evaporate quickly 
  3. Sweat doesn’t evaporate easily from a person who works/exercises hard while wrapped in heavy clothing or protective gear
  4. Heat-related illness is a concern in any weather - anywhere! 

B. Heat Rash & Heat Cramps

Heat Rash

Occurs when sweat ducts get clogged

Heat Cramps

  1. Painful muscle spasms caused by loss of electrolytes from heavy sweating
  2. If workers develop these conditions, immediately get them out of the heat so they can rest.

C. Heat Syncope 

  1. The victim becomes light-headed and faints when blood flow to the brain decreases. This is because blood pressure is lowered when blood vessels dilate to rid the body of heat. 
  2. Blood pressure lowers further when blood volume drops as water is evaporated from the blood. 

D. Recognize - Evaluate - Act

What are the symptoms and to know how to perceive a victim of heat-related illness, analyze and evaluate the symptoms, and act!

Heat Cramps

  1. Have the workman drinks water or an energy drink. Slightly stretch, make a gentle massage, and ice the muscle carefully. 
  2. Search for medical assistance if the workman/employee has heart health issues or if cramps don’t come normally within a specific period (an hour). 

E. The Heat Syncope

  1. Have the workman/employee lie and relaxed down in a cool and tidy area. 
  2. Call for medical help.

F. Heat Exhaustion

  1. Lay the worker down on his or her back in a cool area
  2. Call for medical help 
  3. Remove excessive layers of clothing 
  4. Give a sports drink or water – don’t give anything to drink if the worker vomits 
  5. Cool the worker with a cool water spray or wet cloths and a fan 

G. Heatstroke

  1. Call for medical help immediately! 
  2. While you wait for help to arrive, immediately cool the victim with any means at hand, preferably by immersing the victim up to the neck in cold water.

H. Alternatively:

  1. Move the worker to a cool place and remove clothing down to the underwear, then apply ice packs at the neck, armpits, and groin.
  2. Or, cover the worker with wet towels or cloths or spray him or her with cool water, and fan the worker to quickly evaporate the dampness on the skin. 

I. Catch it Early:

Awareness is vital! 

  1. Both supervisors and workers should be on the lookout for warning signs of heat-related illness.
  2. Safety is everyone’s responsibility.

J. Preventive Measures

  1. Take a light food/meal - The extra or additional calories you take in, the more body your body generates and produces the heat. 
  2. Drink plenty of fluids before work and throughout the day & avoid caffeine 
  3. Wear lightweight clothing
  4. Wide-brimmed hats preserve and protect the workers from direct sunlight and harmful UV rays. 
  5. Heat illnesses are the consequence of not recognizing the warning signs on the job. 
  6. Hot conditions don’t have to be dangerous if you watch for the warning signs and get cooperation from workers to prevent heat-related illness.

HEAT-RELATED ILLNESS TRAINING PPT 

DOWNLOAD THE FILE HERE 

HEAT-RELATED ILLNESS TRAINING PPT 









TO DOWNLOAD MORE FREE HSE DOCUMENTS

CLICK HERE

Wednesday, June 1, 2022

RISK ASSESSMENT FOR CLEARING DRAIN BLOCKAGES AND CLEANING DRAINS

The under discussion risk assessment is very important and the following are some of the points and text derived and taken from the original and editable file for the Risk Assessment for the Clearing Drain Blockages And Cleaning Drains activity. For more quality occupational, health, and safety free documents, log on to my blog site:  

Significant Hazards

Infection and Foreign bodies–feces, contaminated water, needles, glass, soiled dressings

Significant Harms

Infections, Cuts, Needlestick injuries, skin infections dead animals

Existing Controls

  1. Work involving sewage is avoided where possible and contractors are called in to clear drain blockages etc.;
  2. The site Supervisor is instructed to cover open wounds with waterproof dressings;
  3. Appropriate PPE e.g., Safety goggles, impervious gloves, and overalls are provided to reduce the risk of contact with eyes/skin;
  4. Eating, drinking, and smoking are prohibited during the task;
  5. The site Supervisor has had any required inoculations, for example, tetanus.
  6. Proper and essential equipment/machinery is used, for instance, litter picker, tongs, and plunger or drain rods to remove an object;
  7. Hands are not used to free blockages;
  8. Breathing in sewage dust or spray is avoided;
  9. Strict personal hygiene is observed by the site supervisor and hands are washed thoroughly after the task using soap, hot water, and a nail brush;
  10. Contaminated equipment e.g., drain rods are cleaned on-site before storing; the Site supervisor is advised to follow the guidance on dealing with Sharps and Needle-stick Injuries on Health & Safety site.
  11. Adequate first aid equipment is provided, including clean water or sterile wipes for cleansing wounds, and a supply of sterile waterproof, adhesive dressings is provided.
  12. The site Supervisor is advised to consult GP in the event of flu-like illness or fever, particularly where associated with severe headache and skin infections.

Significant Hazards

Slips, trips, falls

Significant Harms

Musculoskeletal injuries, bruising, fractures

Existing Controls

  1. Cautionary signs are put in place before the commencement of the job and left in position until the area is clean and dry;
  2. Any spillages or overflows are cleaned up as soon as possible;
  3. The area is kept free from additional obstructions for the duration of the task.

Significant Hazards

Chemicals / Cleaning products (COSHH)

Significant Harms

Skin irritation, respiratory disorder

Existing Controls

  1. The site Supervisor is competent in safe and correct handling, storage, use, and disposal of chemicals and cleaning products; Products used are specifically for purpose;
  2. The Site Supervisor covers all cuts and abrasions with suitable dressing; all products used are kept out of reach of children;
  3. COSHH risk assessments are completed for the product(s) being used and explained to the employee;
  4. COSHH Manufacturer's Safety Data Sheets are available for products used;
  5. The manufacturer's instructions and COSHH risk assessments for use of specific products are used. The product is properly measured for recommended dilution and added to water. The container cap is replaced;
  6. Appropriate PPE e.g., Safety goggles, impervious gloves, and overalls are provided to reduce the risk of contact with eyes/skin as identified by the COSHH risk assessment; Eating, drinking and smoking are prohibited during the task;
  7. Strict personal hygiene is observed by the site supervisor and hands are washed thoroughly after the task;
  8. All equipment used with chemicals/cleaning products is cleaned and checked before returning to the store;
  9. The Site Supervisor is aware of where and how to obtain First Aid treatment.

Significant Hazards

Pedestrian/vehicular traffic

Significant Harms

Serious injury

Existing Controls

  1. Access to the work area is restricted/monitored;
  2. Designated pedestrian routes are put in place to restrict unauthorized access;
  3. Work is planned for quieter times of the day when reduced/restricted pedestrian access is required to the area;
  4. A safe working area is cordoned off around the area and signage is used as appropriate;
  5. High visibility clothing is worn by the Site Supervisor if working on a traffic route.

Significant Hazards

Weather conditions; high winds, heavy rain, hot weather, etc.

Significant Harms

Fall injuries, sunburn, heat exhaustion

Existing Controls

  1. The site Supervisor assesses the weather conditions before undertaking external work and does not undertake the task if conditions are unsuitable;
  2. Site Supervisor wears clothing appropriate to the weather conditions; Site Supervisor wears clothing to cover skin and wears sunscreen in hot sunshine;
  3. The site Supervisor keeps well hydrated and takes regular breaks in hot weather.

RISK ASSESSMENT FOR CLEARING DRAIN BLOCKAGES AND CLEANING DRAINS 


DOWNLOAD THE FILE HERE 






TO DOWNLOAD MORE HSE DOCUMENTS FOR FREE:

CLICK HERE